Texas freezes data-center projects for a grid, water and subsidy audit
Texas Governor Greg Abbott ordered an audit of every data-center project advancing through the grid interconnection process. The Public Utility Commission of Texas and ERCOT must complete it before any can move forward. ERCOT is considering more than 474 gigawatts of connection requests—over five times its record peak demand—and the state says roughly 90% of the new power requests come from data centers. The audit will examine public subsidies, on-site generation, annual and peak electricity use, water sources and cooling, community effects, and ownership. This is a sharp shift from approving AI infrastructure on promised demand. Texas is asking projects to prove who powers them, who waters them, who pays for them, and who controls them before connecting to a grid shared by everyone.